In a Manufacturing Resource Planning system, which component ensures that materials and products are available for production and delivery to customers while maintaining the lowest possible level of inventory?

Exam Year(s)

DSSSB - 2023,

Answer: B

The component that ensures materials and products are available for production and delivery to customers, while keeping the lowest possible inventory, is the Master Production Schedule in the key. The MPS states what is to be made, in what quantity and when, and the rest of the planning (material requirements, capacity requirements) is derived from it. Capacity requirement planning checks capacity, inventory control tracks stock, and a bill of materials lists the parts of a product, so none of them is the keyed answer.

Please log in or register to report this question.

Loading…
Tags: Material Requirement Planning Questions and Answers || Material Requirement Planning MCQ Questions and Answers || Material Requirement Planning GK Questions and Answers || Material Requirement Planning GK MCQ Questions || Material Requirement Planning Multiple Choice Questions and Answers || Material Requirement Planning GK || GK on Material Requirement Planning || Production Planning and Control Questions and Answers || Production Planning and Control MCQ Questions and Answers || Production Planning and Control GK Questions and Answers || GK on Production Planning and Control