45 men can complete a work in 16 days. After six days when they started working, 30 more men joined them. How many days will they now take to complete the remaining work ?

Exam Year(s)

CBSE Assistant Secretary - 2024,

Answer: B

They will take 6 days.

The whole work is \(45 \times 16 = 720\) man-days. In the first six days, 45 men do \(45 \times 6 = 270\) man-days, leaving 450 man-days. Now \(45 + 30 = 75\) men work:

\[ \frac{450}{75} = 6\ \text{days} \]

10 days is the time the original 45 men would still have needed, and 8 and 12 days do not fit the man-day total.

Please log in or register to report this question.

2.

A can do a work in 14 days and B in 24 days. If they work on it together for 4 days, then the fraction of the work that is left is.

Exam Year(s)

DSSSB - 2023,

Answer: D

The fraction of the work left is 23/42. A does \(\frac{1}{14}\) of the work in a day and B does \(\frac{1}{24}\), so together they do \[ \frac{1}{14} + \frac{1}{24} = \frac{12 + 7}{168} \] \[ \frac{12 + 7}{168} = \frac{19}{168} \] In 4 days they do \(\frac{76}{168} = \frac{19}{42}\). The work left is \[ 1 - \frac{19}{42} = \frac{23}{42} \] The fraction 19/42 is the work done and not the work left, and the others, 18/42, 45/42 and 33/42, do not match.

Another way: take 168 units of work, the lcm of 14 and 24. A does 12 units and B 7 a day, so 4 days make 76 units, and 92 of 168 are left, which is 23/42.

Please log in or register to report this question.

3.

A can lay railway track between two given stations in 18 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in.

Exam Year(s)

DSSSB - 2023,

Answer: C

C alone can do the job in 9 days. A does \(\frac{1}{18}\) of the work in a day and B does \(\frac{1}{12}\), together \(\frac{5}{36}\). With C's help the whole job takes 4 days, so the three together do \(\frac{1}{4}\) per day. \[ \frac{1}{4} - \frac{5}{36} = \frac{9 - 5}{36} \] \[ \frac{4}{36} = \frac{1}{9} \] So C does \(\frac{1}{9}\) of the job per day and needs 9 days alone. The options 13, 11 and 10 days would give C a daily share of less than 1/9.

Please log in or register to report this question.

4.

A work will be completed by Aakash and Bhanu alone in 8 and 18 days, respectively. How soon can the work be completed if they both work alone on alternate days starting with Aakash?

Exam Year(s)

DSSSB PGT - 2023,

Answer: B

The work is completed in \(10\frac{7}{9}\) days. Aakash does 1/8 of the work in a day and Bhanu does 1/18, so two days (one of each) complete \[\frac{1}{8} + \frac{1}{18} = \frac{13}{72}\] Five such pairs, 10 days, complete 65/72 of the work, leaving 7/72. On the eleventh day Aakash works first, and he does 9/72 in a full day, so he needs \[\frac{7/72}{9/72} = \frac{7}{9}\] of a day. The total is \(10\frac{7}{9}\) days. Starting with Bhanu or counting a full day would give the other values listed.

Please log in or register to report this question.

5.

U can complete a work in 20 days; V in 30 days and W in 60 days. V and W assist U on every third day to complete the work. In how many days can U complete the work with the help of V and W?

Exam Year(s)

DSSSB PGT - 2023,

Answer: D

U works every day, and V and W also help on every third day. In a block of three days, U does 3/20 of the work, and on the third day V and W add 1/30 + 1/60 = 1/20.

\[ \tfrac{3}{20} + \tfrac{1}{20} = \tfrac{4}{20} \]

\[ \tfrac{4}{20} = \tfrac{1}{5} \text{ per 3 days} \]

So the work needs 5 blocks of 3 days, which is 15 days. Because the work ends exactly at the end of the fifth block, there is no extra partial block, and the answer is 15 days.

Please log in or register to report this question.

6.

6 men and 8 women can do a work together in 10 days, while 5 men and 15 women can do it in 8 days. How many days will 17 men and 16 women take to finish the work?

Exam Year(s)

DSSSB PGT - 2023,

Answer: B

Equal work is done in the two cases, so 10 days of 6 men and 8 women equal 8 days of 5 men and 15 women.

\[ 10(6m + 8w) = 8(5m + 15w) \]

\[ 20m = 40w \Rightarrow m = 2w \]

The whole work is 10 x (12w + 8w) = 200w. And 17 men and 16 women make 34w + 16w = 50w per day, so they take 200 / 50 = 4 days. The options 3, 6 and 7 do not fit this rate.

Please log in or register to report this question.

7.

A can do a piece of work in 40 days and B can do it in 60 days. In how many days will they finish the work, both working together?

Exam Year(s)

DSSSB PGT - 2023,

Answer: C

They finish in 24 days. In one day A does 1/40 of the work and B does 1/60.

\[ \frac{1}{40} + \frac{1}{60} = \frac{3 + 2}{120} \]\[ = \frac{1}{24} \]

So the work takes 24 days together. 30, 32 and 25 days are wrong because working together must be faster than A alone, and 25 days would need a combined rate of 1/25.

Check with a total of 120 units of work: A does 3 units a day and B does 2, so together they do 5 units a day, and 120 / 5 = 24 days. This also shows the answer is shorter than either person's time alone, which is a quick test for combined-work questions.

Please log in or register to report this question.

8.

Raju can finish a job in 20 days and Vishal can finish the same job in 30 days. In how many days can they finish the job working together?

Exam Year(s)

DSSSB PGT - 2023,

Answer: C

They finish in 12 days. In a day Raju does 1/20 of the job and Vishal 1/30.

\[ \frac{1}{20} + \frac{1}{30} = \frac{3 + 2}{60} \]\[ = \frac{1}{12} \]

The combined time is 12 days. 10 and 6 days would be too fast for these rates, and 25 days is slower than Raju alone.

Check with a total of 60 units of work: Raju does 3 units a day and Vishal 2, so together they do 5 units a day, and 60 / 5 = 12 days. The answer lies between half of the faster person's time (10) and the faster person's own time (20), which agrees with 12.

Please log in or register to report this question.

9.

Sonu can do a piece of work in 30 days. Monu can do it in 20 days, and Siya can do it in 24 days. If they work together, how much time will they take to complete the work?

Exam Year(s)

DSSSB PGT - 2023,

Answer: B

They finish in 8 days. Their daily shares are 1/30, 1/20 and 1/24, and \[ \frac{1}{30} + \frac{1}{20} + \frac{1}{24} \] \[ = \frac{4 + 6 + 5}{120} = \frac{1}{8} \] so together they take 8 days.

5, 6 and 7 days would need daily shares of 1/5, 1/6 and 1/7, more than the combined 1/8.

Please log in or register to report this question.

10.

A can complete a piece of work in 120 days and B can complete it in 150 days. They work together for 20 days. Then B leaves and A alone continues the work. 12 days after that C joins A and the work is completed in 48 more days. In how many days can C complete it if he works alone?

Exam Year(s)

DSSSB PGT - 2023,

Answer: D

C alone would take 240 days. In 20 days A and B finish 20 × (1/120 + 1/150) = 20 × 9/600 = 0.3. A alone works 12 more days for 12/120 = 0.1. That leaves 1 - 0.4 = 0.6, which A and C finish in 48 days: \[ 48\left(\frac{1}{120} + \frac{1}{c}\right) = 0.6 \] \[ \frac{48}{c} = 0.2 \Rightarrow c = 240 \]

200, 210 and 220 days do not satisfy the equation.

The work completed in the first 20 days (0.3) and the next 12 days (0.1) leaves 0.6 for the final stage of 48 days.

Please log in or register to report this question.

Loading…
Tags: Time & Work Questions and Answers || Time & Work MCQ Questions and Answers || Time & Work GK Questions and Answers || Time & Work GK MCQ Questions || Time & Work Multiple Choice Questions and Answers || Time & Work GK || GK on Time & Work || Quantitative Aptitude Questions and Answers || Quantitative Aptitude MCQ Questions and Answers || Quantitative Aptitude GK Questions and Answers || GK on Quantitative Aptitude