61.

In a regular week, there are 5 working days and for each day, the working hours are 8. A man gets Rs. 2.40 per hour for regular work and Rs. 3.20 per hours for overtime. If he earns Rs. 432 in 4 weeks, then how many hours does he work for ?

Exam Year(s)

MPPSC State Service - 2022, MPPSC Forest Service - 2022,

Answer: B

He works 175 hours.

Regular hours in 4 weeks are 4 × 5 × 8 = 160. The earnings separate into regular pay and overtime:

\[ \begin{aligned} 160 \times 2.40 &= 384 \\ 432 - 384 &= 48 \\ 48 \div 3.20 &= 15 \text{ overtime hours} \end{aligned} \]

So he works 160 + 15 = 175 hours. 160 counts only the regular hours, and 180 and 195 would mean more overtime than Rs. 48 pays for.

Please log in or register to report this question.

62.

The daily wages of A and B respectively are ₹ 3.50 and ₹ 2.50. When A finishes a certain work, he gets a total wage of ₹ 63. When B does the same work, he gets a total wage of ₹ 75. If both of them do it together, what is the cost of the work ?

Exam Year(s)

Punjab Civil Service - 2025,

Answer: A

The cost is ₹ 67.50.

A takes \(\frac{63}{3.50} = 18\) days and B takes \(\frac{75}{2.50} = 30\) days to do the work alone. Together they do

\[ \begin{aligned} \frac{1}{18} + \frac{1}{30} &= \frac{5 + 3}{90} = \frac{8}{90} \\ \text{days} &= \frac{90}{8} = 11.25 \end{aligned} \]

Their combined daily wage is ₹ 6, so the cost is \(11.25 \times 6 = 67.50\). Averaging the two totals gives ₹ 69, and the other options do not follow from the times.

Please log in or register to report this question.

63.

Working alone A can do a task in 27 hours and B can do the same in 54 hours. Find C's share (in ₹) if A, B and C get paid ₹ 4,320 for completing a task in 12 hours on which they worked together.

Exam Year(s)

Punjab Civil Service - 2025,

Answer: A

C's share is 1,440 rupees.

In 12 hours A does \(\frac{12}{27} = \frac{4}{9}\) of the task and B does \(\frac{12}{54} = \frac{2}{9}\). C must do the rest:

\[ \begin{aligned} 1 - \tfrac{4}{9} - \tfrac{2}{9} &= \tfrac{3}{9} = \tfrac{1}{3} \\ \text{C's share} &= \tfrac{1}{3} \times 4320 = 1440 \end{aligned} \]

Payment is divided in proportion to work done. 1,920 is A's share and 960 B's.

Please log in or register to report this question.