Machine-translated by Google. Questions are authored in English.
Top

Network Analysis PERT and CPM Questions and Answers

1.

Which of the following is deterministic model?

Exam Year(s)

DSSSB - 2023,

Answer: B

CPM is a deterministic model, as the key states. In the critical path method the durations of activities are known and fixed, so there is no uncertainty, while PERT uses three time estimates (optimistic, most likely and pessimistic) for each activity, and so it is a probabilistic model. The options that name PERT or both, or neither, are wrong.

Please log in or register to report this question.

2.

Activities A to K are required to complete a project. The time estimates and the immediate predecessors of these activities are given in the table. If the project is to be completed in the minimum possible time, the latest finish time for the activity G is ____________ hours.

ActivityTime (hours)Immediate predecessors
A2-
B3-
C2-
D4A
E5B
F4B
G3C
H10D, E
I5F
J8G
K3H, I, J

Exam Year(s)

GATE ME - 2022,

Answer: B

The latest finish time for G is 10 hours.

Forward pass (earliest finish): A 2, B 3, C 2; D 6, E 8, F 7, G 5; H starts after D and E, so finishes at 8 + 10 = 18; I 12; J 13; K starts after H, I and J, at 18, and finishes at 21. The project takes 21 hours along the critical path B-E-H-K.

Backward pass: K must finish by 21, so it starts by 18; J must therefore finish by 18 and start by \(18 - 8 = 10\). G is J's only predecessor, so G must finish by 10 hours.

5 is G's earliest finish, 8 confuses it with J's duration, and 9 has no basis. G has 5 hours of slack, so it is not critical.

Please log in or register to report this question.

Direction for [ Question No: 3 To 4 ] :

Statement for Linked Answer Questions:

For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.

ActivityPredecessorsDuration (days)
a-3
ba4
ca5
da4
eb2
fd9
gc, e6
hf, g2

3.

The critical path for the project is

Exam Year(s)

GATE ME - 2012,

Answer: C

The critical path is a - d - f - h.

List every path through the network and its duration:

  • a - b - e - g - h: 3 + 4 + 2 + 6 + 2 = 17 days
  • a - c - g - h: 3 + 5 + 6 + 2 = 16 days
  • a - d - f - h: 3 + 4 + 9 + 2 = 18 days

The longest path, 18 days, is the critical path and fixes the project duration.

a - b - e - g - h and a - c - g - h are real paths with slack of 1 and 2 days. a - b - c - f - h is not a path at all: c does not follow b, and f follows d, not c.

Please log in or register to report this question.

Answer: A

The critical path remains the same and the total duration changes to 19 days.

Activity f lies on the critical path a - d - f - h, so lengthening it by one day lengthens that path to 3 + 4 + 10 + 2 = 19 days. The other paths (17 and 16 days) are unchanged and still shorter, so the critical path is still a - d - f - h.

Any change to a critical activity changes the project duration, so 'total duration remains the same' is wrong. The critical path would change only if another path became the longest, and 17 days is the length of a non-critical path, not the new project duration.

Please log in or register to report this question.

5.

Gantt chart is used to solve the :

Exam Year(s)

MH SET - 2018, SET Exam - 2018,

Answer: A

A Gantt chart is used for job sequencing problems.

A Gantt chart draws each job as a bar on a time axis, one row per machine or activity, so it shows when each job starts and finishes and where machines sit idle. In operations research it is the standard way to display and check a sequencing solution, for example Johnson's rule for n jobs on two machines, and to read off the total elapsed time.

Inventory problems are solved with EOQ models and stock-level diagrams, and replacement problems with cost-per-period tables, neither of which uses a time chart of job schedules, so 'all of the above' is too broad.

Please log in or register to report this question.

6.

Compute the maximal flow through the following network :

Network from source S to sink N through nodes 1 to 4: arcs S-1 40, S-2 30, 1-3 30, 1-2 5, 1-4 5, 2-4 50, 3-4 25, 3-N 50 and 4-N 30

Exam Year(s)

MH SET - 2021, SET Exam - 2021,

Answer: A

The maximal flow is 70 units.

The two arcs leaving the source, S-1 (40) and S-2 (30), form a cut of capacity 70, so no flow can exceed 70. A flow of 70 can be achieved:

  • S to 1: 40, sent on as 30 to node 3, 5 to node 4 and 5 to node 2.
  • S to 2: 30, plus 5 from node 1, so 35 goes on to node 4.
  • Node 4 receives 5 + 35 = 40: 30 goes to N and 10 to node 3 on the undirected arc 3-4 (capacity 25).
  • Node 3 receives 30 + 10 = 40 and sends it to N (capacity 50).

The flow into N is 40 + 30 = 70, equal to the cut, so by the max-flow min-cut theorem it is maximal. 75 exceeds the cut; 60 and 65 stop short of a flow that is achievable.

Please log in or register to report this question.

7.

In critical path analysis, CPM is :

Exam Year(s)

MH SET - 2021, SET Exam - 2021,

Answer: B

CPM is deterministic in nature.

The critical path method assumes each activity has a single known duration and finds the longest path through the network, which fixes the project time. It is activity-oriented and deterministic.

PERT, by contrast, treats activity times as random (optimistic, most likely and pessimistic estimates) and is event-oriented, so 'event oriented' describes PERT rather than CPM. 'Dynamic in nature' does not describe either.

Please log in or register to report this question.

Loading…

Other Subjects

Tags: Network Analysis PERT and CPM Questions and Answers || Network Analysis PERT and CPM MCQ Questions and Answers || Network Analysis PERT and CPM GK Questions and Answers || Network Analysis PERT and CPM GK MCQ Questions || Network Analysis PERT and CPM Multiple Choice Questions and Answers || Network Analysis PERT and CPM GK || GK on Network Analysis PERT and CPM || Operations Research Questions and Answers || Operations Research MCQ Questions and Answers || Operations Research GK Questions and Answers || GK on Operations Research