51.

None of the following is a cost-effectiveness test applied to a demand side programme except

Answer: C

Correct answer: the total resource cost test

The recognised tests are the participant test, the ratepayer impact measure, the total resource cost test, the programme administrator cost test and the societal test, each taking a different perspective on who bears the costs and who receives the benefits. Diversity, coincidence and plant load factor are load characteristics, not tests of cost effectiveness.

Please log in or register to report this question.

Loading…
Tags: Demand Side Management Questions and Answers || Demand Side Management MCQ Questions and Answers || Demand Side Management GK Questions and Answers || Demand Side Management GK MCQ Questions || Demand Side Management Multiple Choice Questions and Answers || Demand Side Management GK || GK on Demand Side Management || Energy Conservation and Management Questions and Answers || Energy Conservation and Management MCQ Questions and Answers || Energy Conservation and Management GK Questions and Answers || GK on Energy Conservation and Management