Machine-translated by Google. Questions are authored in English.
Top

Small Hydro Power Questions and Answers

1.

Which one of the following criteria is not primary to select the site of a Hydroelectric power plant ?

Exam Year(s)

MH SET - 2025, SET Exam - 2025,

Answer: A

The criterion that is not primary is altitude.

What a hydroelectric site needs is a reliable flow of water and a usable head, the difference in level between the reservoir and the turbines. The absolute altitude of the site above sea level does not matter; a low-lying site with a large drop between the dam and the powerhouse can be excellent.

The other options are primary site criteria. Water availability decides how much energy can be generated through the year. A large catchment area feeds that water into the reservoir. Rocky land, meaning sound rock foundations, is needed to support the dam and resist seepage.

Please log in or register to report this question.

Loading…
Tags: Small Hydro Power Questions and Answers || Small Hydro Power MCQ Questions and Answers || Small Hydro Power GK Questions and Answers || Small Hydro Power GK MCQ Questions || Small Hydro Power Multiple Choice Questions and Answers || Small Hydro Power GK || GK on Small Hydro Power || Renewable Energy Systems Questions and Answers || Renewable Energy Systems MCQ Questions and Answers || Renewable Energy Systems GK Questions and Answers || GK on Renewable Energy Systems