How much work is done in moving a charge of 2 C across two points having a potential difference of 10 V?
DSSSB - 2023,
Answer: B
The work done is 20 J. The work done in moving a charge between two points is the charge multiplied by the potential difference.
\[ W = QV = 2 \times 10 = 20\ \text{J} \]
The value 5 J comes from dividing the voltage by the charge, 40 J from doubling the product, and 200 J from the product of 2, 10 and 10. So the second option is the answer. The joule is defined as one volt times one coulomb, so a potential difference of 1 V does 1 J of work on each coulomb moved across it.