41.

Assertion (A): Water injected into a cement mill does not spoil the cement.
Reason (R): The quantity is controlled so that it evaporates entirely and removes heat as it does so.

Answer: A

Correct answer: Both A and R are true, and R is the correct explanation of A

Both are true and the reason gives the mechanism. The water is dosed so that it flashes to steam within the mill, and the latent heat it absorbs in doing so removes a great deal of heat. None survives to hydrate the cement, so the product is unaffected - the control of the dose is what makes the practice safe.

Please log in or register to report this question.

42.

Consider the following statements about cement additions.
1. Fly ash and slag react with calcium hydroxide from the clinker.
2. Limestone acts largely as a filler with some slight reaction.
3. All additions raise the early strength of the cement.

Answer: B

The first two describe the two mechanisms correctly. The third is wrong, since most additions lower early strength while improving later strength or durability, which is the usual trade. Early strength is given up in return for durability or lower emissions.

Please log in or register to report this question.

Answer: C

Since most of the emission is associated with clinker, replacing part of it with a material that is already a by-product cuts the total proportionately. It remains the most widely applied measure available to the industry.

Please log in or register to report this question.

44.

State whether the following is true or false.
Blended cements are a recent innovation of the last decade.

Answer: D

Correct answer: False

Blended cements are very old. The Romans used volcanic ash with lime, and slag cements have been made industrially since the nineteenth century. What is recent is the scale of their use, driven by the cost of clinker and by the carbon dioxide released in making it.

Please log in or register to report this question.

Answer: A

Correct answer: reacts slowly and benefits from a greater surface area

Slag is latent hydraulic and reacts far more slowly than clinker, so it is ground finer to give the reaction more surface to work on. Note that it is also harder than clinker, not softer - which is why intergrinding leaves it too coarse and separate grinding is the better route.

Please log in or register to report this question.

46.

A cement is 70 per cent clinker, 25 per cent slag and 5 per cent gypsum. How much slag is in a 30-tonne tanker load?

Answer: B

Correct answer: 7.5 tonnes

\[ 0.25 \times 30 = 7.5\ \mathrm{tonnes}. \] The rest is 21 tonnes of clinker and 1.5 of gypsum. Both of those figures appear among the distractors, so the arithmetic is straightforward and the reading of the question is what settles it.

Please log in or register to report this question.

47.

State whether the following is true or false.
A cement mill can be used to grind clinker and slag at different times.

Answer: C

Correct answer: True

Mills are routinely switched between products, and many plants run campaigns of one cement type and then another through the same mill. What the change requires is a cleanout to avoid cross-contamination, and a period of production that is checked before it is accepted into the right silo.

Please log in or register to report this question.

Answer: D

Cement can leave a mill well above a hundred degrees, which stresses silo aeration equipment and risks further dehydration of the gypsum. A cooler on the mill discharge is the usual answer. Cooling also protects the bagging plant and the conveyors.

Please log in or register to report this question.

49.

State whether the following is true or false.
Cement is normally dispatched at ambient temperature.

Answer: A

Correct answer: False

Cement leaves a mill hot - often 100 degrees or more - because nearly all the grinding energy becomes heat. It is cooled to some extent before dispatch, but it is commonly loaded at 60 to 80 degrees rather than at ambient, which is why silo residence time and cooler capacity matter.

Please log in or register to report this question.

50.

Assertion (A): A ready-mixed concrete producer may specify a maximum cement temperature.
Reason (R): Warm cement raises the temperature of the fresh concrete and shortens its working time.

Answer: B

Correct answer: Both A and R are true, and R is the correct explanation of A

Both are true and the reason gives the mechanism. Hot cement raises the temperature of the fresh concrete, and hydration accelerates with temperature, so slump is lost faster and the time available for placing and finishing is shortened. In hot weather that can be decisive, which is why a maximum delivery temperature appears in the specification.

Please log in or register to report this question.

Loading…
Tags: Cement Grinding and Additives Questions and Answers || Cement Grinding and Additives MCQ Questions and Answers || Cement Grinding and Additives GK Questions and Answers || Cement Grinding and Additives GK MCQ Questions || Cement Grinding and Additives Multiple Choice Questions and Answers || Cement Grinding and Additives GK || GK on Cement Grinding and Additives || Cement Technology Questions and Answers || Cement Technology MCQ Questions and Answers || Cement Technology GK Questions and Answers || GK on Cement Technology