A workload runs at 100 per cent capacity for 2 hours a day and 10 per cent for the other 22. What average utilisation would owned hardware sized for the peak achieve?
Answer: A
Two hours at full and twenty-two at a tenth averages about seventeen and a half per cent of the peak capacity. This is exactly the pattern for which elastic provisioning pays for itself. Peak sizing wastes most of the year.