The critical path for the project is
GATE ME - 2012,
Answer: C
The critical path is a - d - f - h.
List every path through the network and its duration:
- a - b - e - g - h: 3 + 4 + 2 + 6 + 2 = 17 days
- a - c - g - h: 3 + 5 + 6 + 2 = 16 days
- a - d - f - h: 3 + 4 + 9 + 2 = 18 days
The longest path, 18 days, is the critical path and fixes the project duration.
a - b - e - g - h and a - c - g - h are real paths with slack of 1 and 2 days. a - b - c - f - h is not a path at all: c does not follow b, and f follows d, not c.