The category of data for planning watershed improvement projects does not include:-
RSMSSB JE - 2025, RSMSSB JE Agriculture - 2025, RSMSSB - 2025,
Answer: D
The data not included is Load sampling data.
Planning a watershed improvement project needs hydrological information (rainfall, runoff, stream flow, groundwater), soil and land use data (soil types, depths, slopes, present use and capability) and economic and social data (land holdings, incomes, population and people's participation).
Load sampling refers to measuring sediment or pollutant loads in a stream, which is a monitoring activity rather than one of the standard categories of planning data, so it is the odd one out.