Chain Rule Questions and Answers

Important Instructions
1.

If 560 workers can complete a project of constructing a bridge in 7 months, then how many more workers will be required to complete the same project in 5 months?

Exam Year(s)

DSSSB PGT - 2023,

Answer: D

224 more workers are needed. The work is 560 × 7 = 3920 worker-months. In 5 months the workers needed are 3920 / 5 = 784. The extra workers are 784 - 560 = 224.

784 is the total required, not the extra, and 400 and 408 do not come from the inverse proportion.

Please log in or register to report this question.

2.

In a ward of a jail, provisions were available for 800 prisoners for 15 days. Some of the prisoners were transferred to some other ward. The same provisions now lasted for 25 days. Find the number of prisoners transferred.

Exam Year(s)

DSSSB PGT - 2023,

Answer: D

320 prisoners were transferred. The provisions equal 800 x 15 = 12,000 prisoner-days. For 25 days they feed 12000/25 = 480 prisoners, so 800 - 480 = 320 were transferred. 200, 1120 and 480 are the other quantities that appear in the working but do not answer the question. Provisions can be treated as a fixed stock of prisoner-days. A stock that lasts 15 days for 800 people can last 25 days only for fewer people, in inverse proportion: 800 x 15 / 25 = 480.

Please log in or register to report this question.

3.

There are 100 students in a hostel. Food provision for them is for 20 days. How long will these provisions last, if 25 more students join the group ?

Exam Year(s)

MPPSC Forest Service - 2024,

Answer: B

The provisions will last 16 days.

The total food is fixed, so the number of students times the number of days is constant:

\[ \begin{aligned} 100 \times 20 &= 125 \times d \\ d &= \frac{2000}{125} = 16 \end{aligned} \]

More students means fewer days, in inverse proportion. Subtracting 25% of 20 days gives 15, which is not offered; 18, 14 and 12 do not keep the product at 2000 student-days.

Please log in or register to report this question.

4.

39 persons can repair a road in 12 days, working 5 hours a day. In how many days will 30 persons, working 6 hours a day, complete the work:

Exam Year(s)

Northern Coalfields Limited - 2020, NCL Technician - 2020,

Answer: B

The work will take 13 days.

The total work in person-hours is the same in both cases:

\[ \begin{aligned} 39 \times 12 \times 5 &= 30 \times d \times 6 \\ 2340 &= 180\,d \\ d &= 13 \end{aligned} \]

Fewer people means more days, but longer working days mean fewer, and the two partly cancel. The other options do not balance: 15 days, for example, gives \(30 \times 15 \times 6 = 2700\) person-hours, more than the 2340 the job needs.

Please log in or register to report this question.

5.

Work in a fort 300 men had provisions for 90 days after 20 days 50 men left the fort. How long would the food last at the same rate?

Exam Year(s)

TNPSC Group 1 - 2017, TNPSC - 2017,

Answer: C

The food will last 84 days more.

After 20 days the provisions left are enough for 300 men for 70 more days. That stock is now shared by 300 - 50 = 250 men:

\[ \begin{aligned} 300 \times 70 &= 250 \times d \\ d &= \frac{21000}{250} = 84\ \text{days} \end{aligned} \]

80 days and 160 days come from forgetting that 20 days have already passed or from using the wrong number of men; with fewer men the food must last longer than 70 days, but only in the ratio 300 : 250.

Please log in or register to report this question.

6.

There are 5 machines that make 5 parts in 5 minutes. How long does it take to make 100 parts in 100 machines?

Exam Year(s)

TNPSC Group 1 - 2025, TNPSC - 2025,

Answer: A

Five machines make 5 parts in 5 minutes, so each machine makes 1 part in 5 minutes.

One hundred machines then make 100 parts in the same 5 minutes, option A. The answers 100, 50 and 30 minutes come from wrongly scaling the time with the number of parts.

The rate per machine is 1 part per 5 minutes, which does not change as more machines are added.

Please log in or register to report this question.

7.

25 labours earn Rs. 3100 in 4 days. Find the earnings of 12 labours in 15 days.

Exam Year(s)

Tripura Public Service Commission - 2015,

Answer: A

The 12 labourers earn Rs. 5580.

Find the wage for one labourer for one day, then scale up.

\[ \begin{aligned} \text{One day's wage} &= \frac{3100}{25 \times 4} = \text{Rs. } 31 \\ \text{Earnings} &= 12 \times 15 \times 31 \\ &= 180 \times 31 = \text{Rs. } 5580 \end{aligned} \]

Check by proportion: the work rises from 100 labourer-days to 180 labourer-days, so the earnings rise in the ratio 180 : 100, and 3100 times 1.8 is 5580. The figures 6580 and 4580 differ from this by exactly a thousand rupees, and 3810 is barely more than the original Rs. 3100 although the labourer-days nearly double.

Please log in or register to report this question.

8.

A garrison of 500 men had provision for 27 days. After 3 days a reinforcement of 300 men arrived. For how many more days will the remaining food last now?

Answer: A

Work in man-days, the quantity that stays fixed however the numbers change. After 3 days the provision left is what 500 men would eat in the remaining \( 27 - 3 = 24 \) days:

\[ \text{food remaining} = 500 \times 24 = 12{,}000 \text{ man-days} \]

The reinforcement brings the strength to \( 500 + 300 = 800 \), so

\[ \text{days} = \frac{12{,}000}{800} = 15 \]

Note the two traps: the 27 must be reduced to 24 before anything else, and the 300 is an addition to the garrison rather than the new total.

Please log in or register to report this question.

9.

2 men and 7 boys can do a piece of work in 14 days; 3 men and 8 boys can do the same in 11 days. Then, 8 men and 6 boys can do three times the amount of this work in 

Answer: B

(2 x 14) men +(7 x 14) boys = (3 x 11) men + (8 x 11) boys

 =>5 men= 10 boys    => 1man= 2 boys

 Therefore, (2 men+ 7 boys) = (2 x 2 +7) boys = 11 boys

 

( 8 men + 6 boys) = (8 x 2 +6) boys = 22 boys.

 Let the required  number of days be x.

 More boys , Less days     (Indirect proportion)

 More work , More days    (Direct proportion)

 Boys22:11Work1 : 3⋮⋮ 14:x

 Therefore, (22 * 1 * x) = (11 * 3 * 14)

=> x = 21 

Hence, the required number of days = 21

Please log in or register to report this question.

10.

If 20 men can build a wall 56 meters long in 6 days , what length of  a similar wall can be  built by 35 men in 3 days?

Answer: D

Let the required length be x meters

 More men, More length built     (Direct proportion) 

Less days, Less length built      (Direct Proportion)

Men20:35Days6 : 3⋮⋮ 56 :x 

=> (20 x 6 x X)=(35 x 3 x 56) 

=> x = 49 

Hence, the required length is 49 m.

Please log in or register to report this question.

Loading…
Tags: Chain Rule Questions and Answers || Chain Rule MCQ Questions and Answers || Chain Rule GK Questions and Answers || Chain Rule GK MCQ Questions || Chain Rule Multiple Choice Questions and Answers || Chain Rule GK || GK on Chain Rule || Quantitative Aptitude Questions and Answers || Quantitative Aptitude MCQ Questions and Answers || Quantitative Aptitude GK Questions and Answers || GK on Quantitative Aptitude