31.

If A and B can do a work in 6 days. B and C can do it in 12 days, C and A can do it in 4 days how many days it would take to finish the same work by all the three together?

Exam Year(s)

TNPSC Group 1 - 2017, TNPSC - 2017,

Answer: B

All three together finish the work in 4 days.

Adding the three pair rates counts each person twice:

\[ \begin{aligned} 2(A + B + C) &= \frac{1}{6} + \frac{1}{12} + \frac{1}{4} = \frac{6}{12} \\ A + B + C &= \frac{1}{4} \end{aligned} \]

So they do a quarter of the work a day and need 4 days. 2 days is the trap of forgetting to halve the combined rate, and 8 or 10 days would be slower than C and A working as a pair. (The figures imply that B does no work at all, since A + B + C comes out equal to C + A, but the answer is still 4 days.)

Please log in or register to report this question.

32.

A and B can complete a work individually in 12 days and 18 days. They started doing the work together but after 4 days A had to leave and B alone completed the remaining work. The whole work was completed in

Exam Year(s)

TNPSC Group 1 - 2017, TNPSC - 2017,

Answer: C

The whole work was completed in 12 days.

In 4 days together they do

\[ \begin{aligned} 4\left(\frac{1}{12} + \frac{1}{18}\right) &= 4 \times \frac{5}{36} \\ &= \frac{5}{9} \end{aligned} \]

The remaining \(\frac{4}{9}\) is done by B alone at \(\frac{1}{18}\) per day, taking \(\frac{4}{9} \times 18 = 8\) days. The total is 4 + 8 = 12 days.

8 days is only B's share, the usual slip; 20 and 30 days are longer than B would take to do the whole job alone.

Please log in or register to report this question.

33.

A does 20% less work than B. If A can complete a piece of work in \(7\frac{1}{2}\) hours then B can do it in

Exam Year(s)

TNPSC Group 1 - 2024, TNPSC - 2024,

Answer: A

A does 20% less work than B, so A's rate is 0.8 of B's. If A takes 7.5 hours, B takes 7.5 x 0.8 = 6 hours, option A.

The other options come from using 1.25 or other wrong factors, such as \(5\frac{1}{2}\), \(6\frac{1}{2}\) and \(6\frac{3}{4}\) hours.

Work is rate times time, so with A's rate at 80 per cent of B's, B takes 80 per cent of A's time. Then 7.5 x 0.8 = 6 hours. The tempting answer of 9.375 hours comes from dividing by 0.8 instead of multiplying, and it is not offered. The other options come from similar slips.

Please log in or register to report this question.

34.

If 4 men can complete a work in 3 days and 3 women can complete that work in 6 days, then which one of the following is not true?

Exam Year(s)

TNPSC Group 1 - 2024, TNPSC - 2024,

Answer: B

4 men finish the work in 3 days, so the work is 12 man-days, and 3 women in 6 days make it 18 woman-days. Then 8 men and 6 women do 8/12 + 6/18 = 1 in a day, 12 men do it in a day, and 18 women do it in a day.

6 men and 8 women do 6/12 + 8/18 = 0.944 of the work in a day, which is less than the whole, so that statement is not true, option B.

Writing each statement in man-days makes the check easy: one man does 1/12 of the work a day and one woman 1/18. For 6 men and 8 women the sum is 6/12 + 8/18 = 17/18 of the work, so the statement that they finish in one day is not true, while the other three statements add up to exactly one day.

Please log in or register to report this question.

35.

One man, 3 women and 4 boys can do a piece of work in 96 hours, 2 men and 8 boys can do it in 80 hours, 2 men and 3 women can do it in 120 hours then 5 men and 12 boys can do it in

Exam Year(s)

TNPSC Group 1 - 2025, TNPSC - 2025,

Answer: C

Let the daily work rates of a man, a woman and a boy be m, w and b. The three conditions are:

\[m+3w+4b=\tfrac{1}{96}\]\[2m+8b=\tfrac{1}{80}\]\[2m+3w=\tfrac{1}{120}\]

Twice the first minus the second gives:

\[6w=\tfrac{1}{48}-\tfrac{1}{80}=\tfrac{1}{120}\]\[w=\tfrac{1}{720}\]

The third gives:

\[2m=\tfrac{1}{120}-\tfrac{1}{240}=\tfrac{1}{240}\]\[m=\tfrac{1}{480}\]

The second gives:

\[8b=\tfrac{1}{80}-\tfrac{1}{240}=\tfrac{1}{120}\]\[b=\tfrac{1}{960}\]

Then:

\[5m+12b=\tfrac{10}{960}+\tfrac{12}{960}=\tfrac{11}{480}\]

so the time is 480/11 = 43 7/11 hours, option C.

Please log in or register to report this question.

36.

8 Men working 9 hours a day complete a piece of work in 20 days. In how many days can 12 men working for 10 hours a day complete the same piece of work?

Exam Year(s)

TNPSC Group 1 - 2025, TNPSC - 2025,

Answer: D

The total work is 8 men x 9 hours x 20 days = 1,440 man-hours.

The new group works 12 men x 10 hours = 120 man-hours a day, so \[\text{days}=\tfrac{1440}{120}=12.\]

So the work takes 12 days, option D. The values 9, 10 and 11 days would give fewer than 1,440 man-hours.

The same method works for any problem of men, hours and days: men times hours times days stays constant for a fixed amount of work.

Please log in or register to report this question.

37.

A and B together can do a work in 6 days. If A can alone do the work in 18 days, then the number of days required for B to finish the work is

Exam Year(s)

Tripura Public Service Commission - 2026,

Answer: B

B alone would take 9 days.

Work in fractions of the job per day. Together they do \(\frac{1}{6}\) a day and A alone \(\frac{1}{18}\):

\[ \begin{aligned} \text{B's rate} &= \frac{1}{6} - \frac{1}{18} \\ &= \frac{3 - 1}{18} = \frac{1}{9} \end{aligned} \]

So B finishes the work in 9 days. Check: \(\frac{1}{18} + \frac{1}{9} = \frac{3}{18} = \frac{1}{6}\). 12 comes from subtracting days (\(18 - 6\)) instead of rates, a common mistake; 15 has no basis.

Please log in or register to report this question.

38.

A, B and C can do a piece of work in 8 days, 12 days and 15 days respectively. How long will they take to finish it if they work together ?

Exam Year(s)

Tripura Public Service Commission - 2019,

Answer: C

Working together they take \(3\frac{7}{11}\) days.

Add the work each person does in one day:

\[ \begin{aligned} \tfrac{1}{8} + \tfrac{1}{12} + \tfrac{1}{15} &= \tfrac{15 + 10 + 8}{120} \\ &= \tfrac{33}{120} = \tfrac{11}{40} \end{aligned} \]

So together they finish \(\frac{11}{40}\) of the work a day, and the whole work takes

\[ \frac{40}{11} = 3\tfrac{7}{11}\ \text{days} \]

The answer must be less than 8 days, the time of the fastest worker alone, and well under it with three people working. 5 and 6 days are too long, and \(4\frac{5}{11}\) comes from an arithmetic slip in the common denominator.

Please log in or register to report this question.

39.

If it takes two workers, working separately but at the same speed, 2 hours and 40 minutes to complete a particular task, about how long will it take one worker, working at the same speed, to complete the same task alone?

Exam Year(s)

Tripura Public Service Commission - 2025,

Answer: D

One worker alone takes 5 hrs. 20 min.

Two workers at the same speed, working on the task together, finish it in 2 hours 40 minutes, which is 160 minutes. One worker does half the work per minute, so takes twice as long: \(2 \times 160 = 320\) minutes, which is 5 hours 20 minutes.

1 hr. 20 min halves the time instead of doubling it. 4 hrs. 40 min and 5 hrs. come from adding instead of doubling, or from rounding.

Please log in or register to report this question.

40.

Two men can do a piece of work in 6 hrs. and 4 hrs. respectively. After the first has worked for 2 hrs. he is joined by the other. Then the time taken to complete the work will be

Exam Year(s)

Tripura Public Service Commission - 2021,

Answer: A

The work is completed 1.6 hrs. after the second man joins.

The first man does \(\frac{1}{6}\) of the work per hour and the second \(\frac{1}{4}\). In his first 2 hours alone the first man does \(\frac{2}{6} = \frac{1}{3}\), leaving \(\frac{2}{3}\) for the two together:

\[ \begin{aligned} \text{joint rate} &= \frac{1}{6} + \frac{1}{4} = \frac{5}{12} \\ \text{time} &= \frac{2}{3} \div \frac{5}{12} = \frac{8}{5} = 1.6\ \text{hrs} \end{aligned} \]

The question asks for the time taken after the two start working together; counting the first man's 2 hours as well would give 3.6 hours, which is not offered. 2.4 hours is how long the two together would need for the whole job.

Please log in or register to report this question.

Loading…
Tags: Time & Work Questions and Answers || Time & Work MCQ Questions and Answers || Time & Work GK Questions and Answers || Time & Work GK MCQ Questions || Time & Work Multiple Choice Questions and Answers || Time & Work GK || GK on Time & Work || Quantitative Aptitude Questions and Answers || Quantitative Aptitude MCQ Questions and Answers || Quantitative Aptitude GK Questions and Answers || GK on Quantitative Aptitude