Delivered equipment costing 3 million with a Lang factor of 4.7 gives a total installed cost of about
Answer: C
Multiplying the equipment cost by the factor gives 14.1 million, the balance covering piping, instruments, structures, erection and engineering. It is a budget-class figure and should be quoted with an accuracy of the order of plus or minus thirty per cent.