Benefit Cost Analysis Questions and Answers

Answer: A

Correct answer: public sector projects

A private firm can measure its returns in its own receipts, but a public agency’s project produces benefits accruing to people who pay nothing directly - time saved, floods averted, lives spared. Benefit cost analysis exists to bring those into the same account as the money spent, which is why it belongs to the public sector.

Please log in or register to report this question.

Answer: C

Noise from a new road, land taken from farmers and habitat destroyed are disbenefits, and they enter the analysis with a negative sign. Where they are put, in the numerator or the denominator, is what distinguishes the two ratio conventions.

Please log in or register to report this question.

Answer: D

Correct answer: the government or sponsoring agency

The costs in the denominator are the sponsor’s outlays: construction, land, operation and maintenance. What the public gives up appears elsewhere, as a disbenefit, and the contractor’s costs enter only through the price the agency pays. Keeping the perspective consistent is what prevents the same effect being counted twice.

Please log in or register to report this question.

5.

The conventional benefit cost ratio is benefits less disbenefits divided by

Answer: A

Correct answer: costs

\[ B/C = \frac{B - D}{C}. \] Disbenefits are subtracted from benefits in the numerator, leaving the denominator as the agency’s costs alone. This is the conventional form, and it must be identified as such because the modified form gives a different number from the same figures.

Please log in or register to report this question.

Answer: B

Correct answer: denominator, added to costs

\[ B/C_{mod} = \frac{B}{C + D}. \] The modified convention treats a disbenefit as a cost borne by the public rather than as a benefit forgone. Since it moves a positive quantity from being subtracted above to being added below, it always gives a smaller ratio than the conventional form for an acceptable project.

Please log in or register to report this question.

7.

The two ratio conventions give different numerical values but the same

Answer: C

Correct answer: accept-or-reject decision

Both conventions cross unity at exactly the point where net present worth crosses zero, since \( B - D > C \) and \( B > C + D \) are the same inequality rearranged. The numerical values differ and so may rankings, but whether a project passes does not depend on which form was used.

Please log in or register to report this question.

8.

A project is acceptable if its benefit cost ratio is

Answer: D

Correct answer: at least one

A ratio of one means the discounted benefits net of disbenefits exactly equal the discounted costs, so the project just earns the discount rate. Above one it is worth doing; below one it is not. The discount rate is already inside the calculation, which is why the criterion is unity rather than the rate itself.

Please log in or register to report this question.

9.

A benefit cost ratio of exactly one corresponds to a present worth of

Answer: A

Correct answer: zero

\[ \frac{B-D}{C} = 1 \quad\Longleftrightarrow\quad B - D - C = 0. \] The two criteria are the same statement written differently, which is why benefit cost analysis and present worth analysis never disagree about whether a single project should proceed.

Please log in or register to report this question.

Answer: B

The ratio is unchanged whether both are annualised or both discounted to the present, since the same capital recovery factor divides out of numerator and denominator alike. Mixing the two bases produces a meaningless number.

Please log in or register to report this question.

Loading…
Tags: Benefit Cost Analysis Questions and Answers || Benefit Cost Analysis MCQ Questions and Answers || Benefit Cost Analysis GK Questions and Answers || Benefit Cost Analysis GK MCQ Questions || Benefit Cost Analysis Multiple Choice Questions and Answers || Benefit Cost Analysis GK || GK on Benefit Cost Analysis || Engineering Economics Questions and Answers || Engineering Economics MCQ Questions and Answers || Engineering Economics GK Questions and Answers || GK on Engineering Economics