Answer: C

Correct answer: used in the core of the breakwater enclosing it

Dredged material from the basin is generally unsuitable as armour but perfectly good as core, so it is placed inside the breakwater under the underlayers and armour. This kills two costs at once - the material need not be disposed of, and core need not be imported - and it is why the excavation and the breakwater are normally planned together as one earthworks balance.

Please log in or register to report this question.

92.

Assertion (A): Balancing cut and fill is a significant economy in harbour construction.
Reason (R): Excavated material used in the works avoids both disposal and import costs.

Answer: D

Correct answer: Both A and R are true, and R is the correct explanation of A

Both are true and the reason states the double saving. Marine disposal requires a licence, a haul to the disposal ground and the vessel time to get there; imported core requires quarrying, haulage and placing. Using the excavated material in the works avoids both, and on a large harbour the sums involved are a substantial fraction of the contract. It is the marine equivalent of balancing cut and fill on a road scheme.

Please log in or register to report this question.

Loading…
Tags: Seawalls Groynes and Breakwaters Questions and Answers || Seawalls Groynes and Breakwaters MCQ Questions and Answers || Seawalls Groynes and Breakwaters GK Questions and Answers || Seawalls Groynes and Breakwaters GK MCQ Questions || Seawalls Groynes and Breakwaters Multiple Choice Questions and Answers || Seawalls Groynes and Breakwaters GK || GK on Seawalls Groynes and Breakwaters || Coastal Engineering Questions and Answers || Coastal Engineering MCQ Questions and Answers || Coastal Engineering GK Questions and Answers || GK on Coastal Engineering