11.

A and B can complete a piece of work in 12 days and 18 days, respectively. A begins to do the work and they work alternately on their turn. The whole work will be completed in:

Exam Year(s)

DSSSB PGT - 2023,

Answer: A

The work is completed in 14 1/3 days. A does 1/12 and B does 1/18 of the work a day. Two days (A then B) complete 1/12 + 1/18 = 5/36. Seven such pairs, 14 days, complete 35/36. The remaining 1/36 is done by A on the 15th day in (1/36)/(1/12) = 1/3 day. So the total is 14 1/3 days. 15 1/3 would add a whole extra day and the other two values give wrong remainders. Because they work alternately and A is faster, the pair of days does not end in a whole number of days, and the fractional last day is done by A alone. Option 15 1/3 would add an extra day with B, which is not needed because only 1/36 of the work remains.

Please log in or register to report this question.

12.

150 men were employed to finish a work in 90 days. After 45 days it was found that only \(\frac{2}{5}\) of the work was done. How many more men must be employed to finish the work in the stipulated time?

Exam Year(s)

DSSSB PGT - 2023,

Answer: D

75 more men are needed. In the first 45 days 150 men did 2/5 of the work, leaving 3/5 to be done in the remaining 45 days. If 150 men do 2/5 in 45 days then the 3/5 needs 150 x (3/5)/(2/5) = 225 men for 45 days. So 225 - 150 = 75 more are required. 150 and 125 are too many, and 95 is not enough. The remaining work is 3/5 of the whole in 45 days. Since 150 men finished 2/5 in 45 days, the work done per man in 45 days is 2/5 divided by 150, so for 3/5 the men needed are 150 x 3/2 = 225, requiring 75 additional men.

Please log in or register to report this question.

13.

Working together X, Y and Z can complete a certain work in 20 days. X and Y together can complete 40 % of it in 10 days and Y and Z together can complete it in 40 days. In how many days can X and Z complete 35 % of the original work?

Exam Year(s)

DSSSB - 2023,

Answer: B

X and Z can complete 35 % of the work in 10 days. X, Y and Z together do 1/20 of the work per day. X and Y together do 40 % in 10 days, so 1/25 per day, and Y and Z together do 1/40 per day.

\[ Z = \frac{1}{20} - \frac{1}{25} = \frac{1}{100} \]

\[ X = \frac{1}{20} - \frac{1}{40} = \frac{1}{40} \]

\[ X + Z = \frac{1}{40} + \frac{1}{100} = \frac{7}{200} \]

\[ \text{Time} = \frac{0.35}{7/200} = 10 \text{ days} \]

The options 9, 12 and 15 days do not equal 0.35 divided by 7/200, so the second option is the answer.

Please log in or register to report this question.

14.

Rakesh is twice as efficient as Shalini. If he can finish a piece of work in 25 days less than Shalini, then how many days does Shalini require to complete the same work?

Exam Year(s)

DSSSB - 2023,

Answer: C

Shalini needs 50 days.

Rakesh is twice as efficient, so he takes half of Shalini's time. If Shalini takes S days, Rakesh takes S/2 days, and the difference is 25 days.

\[ S-\frac{S}{2}=25 \Rightarrow S=50 \]

35, 45 and 60 do not satisfy this condition.

The check is easy: if Shalini takes 50 days, Rakesh takes half of that, 25 days, and 50 − 25 = 25 days less, as stated. Twice the efficiency always means half the time for the same work.

Please log in or register to report this question.

15.

30 women can do a certain work in 24 days. 24 men can complete the same work in 21 days. What is the ratio between the capacity of a man and a woman, respectively?

Exam Year(s)

DSSSB - 2023,

Answer: A

The ratio is 10:7.

The work equals 30 × 24 = 720 woman-days and also 24 × 21 = 504 man-days. So 720 woman-days equal 504 man-days, which means one man does as much as 720/504 = 10/7 women.

\[ \text{man : woman}=\frac{10}{7} \]

7:10 is the inverse and 3:5 and 5:3 do not match the numbers.

You can check the answer by computing the work of one man and one woman in a day. One woman does 1/720 of the work per day and one man does 1/504. The ratio man to woman is (1/504) : (1/720), which equals 720 : 504, and dividing by 72 gives 10 : 7.

Please log in or register to report this question.

16.

Ananth takes 6 hours and Bharath takes 4 hours to read a book. Both started reading copies of the book at the same time. After how many hours is the number of pages to be read by Ananth, twice that to be read by Bharath? Assume Ananth and Bharath read all the pages with constant pace.

Exam Year(s)

GATE AG - 2016,

Answer: C

After 3 hours.

Take the book as 1 unit. Ananth reads \(1/6\) per hour and Bharath \(1/4\) per hour, so after \(t\) hours the parts still to be read are \(1 - t/6\) and \(1 - t/4\).

\[ \begin{aligned} 1 - \frac{t}{6} &= 2\left(1 - \frac{t}{4}\right) \\ \frac{t}{2} - \frac{t}{6} &= 1 \\ \frac{t}{3} = 1 &\Rightarrow t = 3 \end{aligned} \]

Check: after 3 hours Ananth has half the book left and Bharath a quarter, and a half is twice a quarter. After 1 or 2 hours Ananth's remainder is less than twice Bharath's (5/6 against 3/2, 2/3 against 1); at 4 hours Bharath has finished while Ananth still has a third to read.

Please log in or register to report this question.

17.

Seven machines take 7 minutes to make 7 identical toys. At the same rate, how many minutes would it take for 100 machines to make 100 toys?

Exam Year(s)

GATE ME - 2018, GATE XE - 2018,

Answer: B

It takes 7 minutes.

Seven machines make 7 toys in 7 minutes, so each machine makes one toy in 7 minutes. A hundred machines working at the same time each make one toy in those 7 minutes, giving 100 toys.

100 and 700 come from scaling the time with the number of toys and forgetting that the number of machines grows in the same proportion. 1 minute would need each machine to work seven times faster.

Please log in or register to report this question.

18.

A can do a piece of work in 7 days of 9 hours each day and B can do it in 6 days of 7 hours each day. then how many days they will take to do it, working together 8 hours a day:

Exam Year(s)

HPPSC HPAS - 2021,

Answer: C

Working together 8 hours a day, they need about 3 days.

Convert each worker's time to hours: A needs \(7 \times 9 = 63\) hours and B needs \(6 \times 7 = 42\) hours.

\[ \begin{aligned} \text{per hour} &= \frac{1}{63} + \frac{1}{42} = \frac{5}{126} \\ \text{hours} &= \frac{126}{5} = 25.2 \\ \text{days} &= \frac{25.2}{8} = 3.15 \end{aligned} \]

The exact figure is 3.15 days of 8 hours, which the options round to 3 days. 2 days (16 hours) is too short, since together they need more than 25 hours. 5 and 6 days are too long: B alone needs 42 hours, about 5.25 days of 8 hours, and adding A can only shorten that.

Please log in or register to report this question.

19.

Praveen can complete a piece of work in 30 days, while Mohit can finish it in 25 days. They work together for 10 days, after which Praveen leaves. How many more days will Mohit take to complete the remaining work ?

Exam Year(s)

HPPSC HPAS - 2025,

Answer: B

Mohit needs 20/3 days more.

Praveen does 1/30 of the work a day and Mohit 1/25. Together in 10 days they finish:

\[ \begin{aligned} 10 \left( \tfrac{1}{30} + \tfrac{1}{25} \right) &= 10 \times \tfrac{11}{150} \\ &= \tfrac{11}{15} \end{aligned} \]

That leaves \(\tfrac{4}{15}\) of the work for Mohit alone:

\[ \tfrac{4}{15} \times 25 = \tfrac{20}{3} \text{ days} \]

That is 6 days and 8 hours. 16/3 and 14/3 days would leave work undone, and 22/3 days is more than the remaining work needs.

Please log in or register to report this question.

20.

Consider the following statements :

1. If 5 workers can finish a job in 10 days, then 10 workers can finish it in 6 days.
2. If four pencils cost ₹ 20, then 10 pencils cost ₹ 55.
3. If two litres of milk cost ₹ 50, then 4 litres cost ₹ 120.

How many of the statements given above are correct?

Exam Year(s)

Haryana Civil Services - 2026, HPSC - 2026,

Answer: D

None of the statements is correct.

Statement 1: 5 workers × 10 days = 50 worker-days, so 10 workers need \(50 / 10 = 5\) days, not 6.

Statement 2: four pencils for ₹ 20 is ₹ 5 each, so 10 pencils cost ₹ 50, not ₹ 55.

Statement 3: two litres for ₹ 50 is ₹ 25 a litre, so 4 litres cost ₹ 100, not ₹ 120.

Each statement is a simple proportion with a wrong figure, so every option claiming one or more correct statements fails.

Please log in or register to report this question.

Loading…
Tags: Time & Work Questions and Answers || Time & Work MCQ Questions and Answers || Time & Work GK Questions and Answers || Time & Work GK MCQ Questions || Time & Work Multiple Choice Questions and Answers || Time & Work GK || GK on Time & Work || Quantitative Aptitude Questions and Answers || Quantitative Aptitude MCQ Questions and Answers || Quantitative Aptitude GK Questions and Answers || GK on Quantitative Aptitude