Retrofitting of Structures Questions and Answers

Answer: A

A wall collects a large share of the storey shear and delivers a large overturning moment to its base, and the existing footings were never designed for it. New pile caps or raft extensions are commonly the largest single item of the work.

Please log in or register to report this question.

Answer: B

A braced bay is light, can be installed from outside in some cases, and interferes less with the use of the building than a solid wall. The connections to the existing frame and the demand on the foundations remain the difficult parts.

Please log in or register to report this question.

Answer: C

Correct answer: the building must stay in use during the works

An exoskeleton is built outside the envelope, so the interior is scarcely touched and the occupants remain in place. That is its principal justification, and it is bought at the cost of appearance and of new foundations outside the existing footprint.

Please log in or register to report this question.

Answer: D

Removing heavy floor finishes, replacing masonry partitions with light ones, or taking off an upper storey all reduce the demand in direct proportion. It is one of the few measures that improves matters without adding anything new to the structure.

Please log in or register to report this question.

Answer: A

Mass removed from the top has the greatest effect on base shear and on overturning, because of the height at which the code applies the force. It is drastic and reduces the lettable area, so it is used where nothing gentler will serve.

Please log in or register to report this question.

Answer: B

Correct answer: heritage buildings and essential facilities

Base isolation reduces the demand on the superstructure rather than strengthening it, so the fabric above can be left alone - which is what a heritage building needs. And it keeps the structure close to elastic, so an essential facility remains usable after the earthquake rather than merely standing.

Please log in or register to report this question.

Answer: C

Cutting drift by taking energy out of the response can bring the existing members within their capacity, so the intervention is confined to a few bays. That makes the work far less disruptive than jacketing columns throughout an occupied building.

Please log in or register to report this question.

Answer: D

Moving the centre of stiffness away from the centre of mass produces twist under shaking and overloads the far corners. Retrofit schemes are therefore checked for the irregularity they introduce as well as the one they remove.

Please log in or register to report this question.

Answer: A

Correct answer: creating a soft storey lower down

Stiffening part of a building concentrates the deformation in whatever is left unstiffened, so the storey below the strengthened region takes the drift the storeys above no longer do. A retrofit must therefore be checked over the whole height - strengthening a part can make the whole worse.

Please log in or register to report this question.

Answer: B

The new cage provides confinement, additional longitudinal steel and additional section, so both strength and ductility improve. Continuity of the new bars through the floors is the detail that decides whether the jacket works.

Please log in or register to report this question.

Loading…
Tags: Retrofitting of Structures Questions and Answers || Retrofitting of Structures MCQ Questions and Answers || Retrofitting of Structures GK Questions and Answers || Retrofitting of Structures GK MCQ Questions || Retrofitting of Structures Multiple Choice Questions and Answers || Retrofitting of Structures GK || GK on Retrofitting of Structures || Earthquake Engineering Questions and Answers || Earthquake Engineering MCQ Questions and Answers || Earthquake Engineering GK Questions and Answers || GK on Earthquake Engineering