Machine-translated by Google. Questions are authored in English.
Top

Time & Work Questions and Answers

Important Instructions
21.

Which of the following statements is/are correct?

1. If 5 workers complete a task in 12 days, then 10 workers can complete the same task in 5 days.
2. If 8 workers complete a task in 14 days, then 4 workers can complete the same task in 30 days.

Select the answer using the codes given below:

Exam Year(s)

Haryana Civil Services - 2026, HPSC - 2026,

Answer: D

Neither 1 nor 2 is correct.

Work is workers times days and stays constant for the same task.

\[ \begin{aligned} 5 \times 12 &= 60 \Rightarrow \tfrac{60}{10} = 6 \text{ days, not } 5 \\ 8 \times 14 &= 112 \Rightarrow \tfrac{112}{4} = 28 \text{ days, not } 30 \end{aligned} \]

Both statements misstate the result of an inverse proportion: doubling the workforce halves the time (12 to 6), and halving it doubles the time (14 to 28).

Please log in or register to report this question.

22.

Which of the following is/are correct?

1. A and B together can do a piece of work in 12 days. B and C together can do it in 15 days. If A is twice as good a workman as C, then B alone can finish the work in 20 days.
2. If Ram can do a piece of work in 10 days and Shyam can complete the same work in 6 days, then both of them together complete the work within 4 days.

Select the answer using the code given below:

Exam Year(s)

Haryana Civil Services - 2026, HPSC - 2026,

Answer: C

Both 1 and 2 are correct.

Statement 1: write the daily work rates as a, b, c with a = 2c.

\[ \begin{aligned} a + b &= \tfrac{1}{12},\ \ b + c = \tfrac{1}{15} \\ (a + b) - (b + c) &= c = \tfrac{1}{12} - \tfrac{1}{15} = \tfrac{1}{60} \\ b &= \tfrac{1}{15} - \tfrac{1}{60} = \tfrac{1}{20} \end{aligned} \]

Here a − c = c because a = 2c. So B alone takes 20 days. True.

Statement 2: together Ram and Shyam do \(\tfrac{1}{10} + \tfrac{1}{6} = \tfrac{8}{30}\) a day, so they take \(30/8 = 3.75\) days, which is within 4 days. True.

Please log in or register to report this question.

23.

Consider the following statements:

1. If A completes a job in 10 days and B in 15 days, then together they will complete it in 6 days.
2. If 6 workers complete a job in 8 days, then 3 workers will complete it in 16 days (same efficiency).
3. If A is twice as efficient as B, then A takes half the time taken by B to complete the same work.

How many of the statements given above are correct?

Exam Year(s)

Haryana Civil Services - 2026, HPSC - 2026,

Answer: C

All three statements are correct.

Statement 1: \(\tfrac{1}{10} + \tfrac{1}{15} = \tfrac{3 + 2}{30} = \tfrac{1}{6}\), so together they take 6 days.

Statement 2: the job is \(6 \times 8 = 48\) worker-days, so 3 workers need \(48 / 3 = 16\) days.

Statement 3: if A does twice B's work per day, A finishes the same job in half B's time, since time is inversely proportional to efficiency.

Each statement applies the inverse relation between rate and time correctly, so the answer is all three.

Please log in or register to report this question.

24.

A man can plough a field alone in 20 days. His wife can plough it in 25 days. When they plough the field with their son they can plough it in 5 days. How many days would the son take if he were to plough the field alone?

Exam Year(s)

Kerala PSC KAS - 2020,

Answer: B

The son alone would take \(9\frac{1}{11}\) days.

Work out how much of the field each person ploughs in one day and subtract the parents' share from the family's total.

\[ \begin{aligned} \text{son} &= \frac{1}{5} - \frac{1}{20} - \frac{1}{25} \\ &= \frac{20 - 5 - 4}{100} \\ &= \frac{11}{100} \end{aligned} \]

So the son ploughs \(\frac{11}{100}\) of the field a day and needs \(\frac{100}{11} = 9\frac{1}{11}\) days.

Check that the three together finish in 5 days:

\[ \begin{aligned} \frac{1}{20} + \frac{1}{25} + \frac{11}{100} &= \frac{5 + 4 + 11}{100} \\ &= \frac{20}{100} = \frac{1}{5} \end{aligned} \]

The other options differ only in the whole number, so the subtraction alone decides them.

Please log in or register to report this question.

25.

A is twice as good as workman as B and therefore able to finish a piece of work in 30 days less than B. In how many days can they complete the whole work; working together?

Exam Year(s)

MP Lab Technician - 2015,

Answer: A

Working together they finish in 20 days.

A is twice as efficient as B, so B takes twice as long as A. If A takes \(x\) days, B takes \(2x\), and the difference is 30 days:

\[ \begin{aligned} 2x - x &= 30 \Rightarrow x = 30 \\ \text{A} &= 30 \text{ days}, \ \text{B} = 60 \text{ days} \end{aligned} \]

\[ \begin{aligned} \frac{1}{30} + \frac{1}{60} &= \frac{3}{60} \\ &= \frac{1}{20} \end{aligned} \]

So together they do one-twentieth of the work a day and need 20 days.

60 days is B's time working alone. 40 and 80 days are longer than A's own 30 days, which is impossible once B helps.

Please log in or register to report this question.

26.

12 men and 20 women can do a construction work in 6 days. The ratio of work force of men to women is 5 : 4. Which of the following option is wrong to complete the same work in 3 days ?

Exam Year(s)

MPPSC Forest Service - 2022,

Answer: D

The wrong option is 48 men are employed.

Take a man's daily work as 5 units and a woman's as 4 (ratio 5 : 4).

\[ \begin{aligned} \text{work} &= 6 \times (12 \times 5 + 20 \times 4) \\ &= 6 \times 140 = 840 \\ \text{per day in 3 days} &= 840/3 = 280 \end{aligned} \]

24 men and 40 women give 120 + 160 = 280, 56 men give 280, and 70 women give 280, so all three finish in 3 days. 48 men give only 240 units a day, so they cannot finish in 3 days.

Please log in or register to report this question.

27.

Rindia can do a job in 10 days. Rakesh can do the same job in 5 days. In how many days they can complite the job if they work together?

Answer: B

Rindia can do a job in 10 days.
So efficiency of Rindia = 100/10 = 10%
Similarly, Rakesh's efficiency = 100/5 = 20%
Combined efficiency of Rindia + Rakesh per day becomes = 20 + 10 = 30 %
Now, we have to find out the number of days taken by both Rindia and Rakesh to do 100% work,
Since they can do 30% work in 1 day,
So, they will 100% work in 100/30 = 3.33 days

Please log in or register to report this question.

28.

A can do a work in 30 days and B can complete the same work in 45 days. In how many days the work will be completed if both work together?

Answer: D

A completes the work in 30 days. A's one day work will be 1/30 of the work. B's one day work will be 1/45 of the work.
Both work together, in one day, 1/30 + 1/45 of the work will get over.
In one day 75/1350 of the work will get over. Which means the work will get over in 1350/75 days. The work will get completed in 18 days.

Please log in or register to report this question.

29.

Reema can complete a piece of work in 12 days while Seema can the same work in 18 days. If they both work together, then how many days will be required to finish the work?

Answer: B

A's one day work = 1
12
B's one day work = 1
18
(A + B)'s one day work = 1 + 1 = (18 + 12) = 30 = 1
12 18 (12 x 18) 216 7.2

Together, A & B will finish the work in 7.2 days.

Please log in or register to report this question.

30.

A can do a work in 24 days and B can complete the same work in 12 days. In how many days the work will be completed if both work together?

Answer: C

A completes the work in 24 days. A's one day work will be 1/24 of the work.
B's one day work will be 1/12 of the work.
Both work together, in one day, 1/24 + 1/12 of the work will get over.
In one day 36/288 of the work will get over. Which means the work will get over in 288/36 days.
The work will get completed in 8 days.

Please log in or register to report this question.

Loading…
Tags: Time & Work Questions and Answers || Time & Work MCQ Questions and Answers || Time & Work GK Questions and Answers || Time & Work GK MCQ Questions || Time & Work Multiple Choice Questions and Answers || Time & Work GK || GK on Time & Work || Quantitative Aptitude Questions and Answers || Quantitative Aptitude MCQ Questions and Answers || Quantitative Aptitude GK Questions and Answers || GK on Quantitative Aptitude