Assignment Problems Questions and Answers

1.

Consider the following assignment problem

Jobs / MachinesABCD
I10251520
II1530515
III35201224
IV17252420

The solution to this problem is given by :

Exam Year(s)

MH SET - 2018, SET Exam - 2018,

Answer: A

The optimal assignment is I → A, II → C, III → B, IV → D.

Its total cost is the lowest possible:

\[ 10 + 5 + 20 + 20 = 55 \]

The Hungarian method (or checking all 24 assignments) confirms that no other assignment costs less; the next best cost 62. The other options cost more: I → A, II → B, III → C, IV → D costs 10 + 30 + 12 + 20 = 72; I → B, II → A, III → C, IV → D costs 25 + 15 + 12 + 20 = 72; and I → B, II → C, III → A, IV → D costs 25 + 5 + 35 + 20 = 85.

Please log in or register to report this question.

2.

Consider the following assignment cost matrix :

Machines / JobsJ1J2J3J4
M110978
M25877
M35465
M42345

The optimal cost of assignment is :

Exam Year(s)

MH SET - 2019, SET Exam - 2019,

Answer: C

The optimal cost is 20.

Hungarian method. Subtract each row's minimum (7, 5, 4, 2), then each column's minimum (0, 0, 0, 1). That removes 19 in total, so no assignment can cost less than 19.

In the reduced matrix, M2 and M4 both have their only zero in column J1, so a complete assignment of zeros is impossible. Covering the zeros and adjusting by the smallest uncovered value adds one more unit, giving 20, and then a full set of independent zeros exists:

\[ \begin{aligned} & M_{1} \to J_{3} = 7,\ M_{2} \to J_{1} = 5 \\ & M_{3} \to J_{4} = 5,\ M_{4} \to J_{2} = 3 \\ & \text{Total} = 7 + 5 + 5 + 3 = 20 \end{aligned} \]

Checking every one of the 24 assignments confirms that none costs less than 20, so 18 is impossible, and 24 and 26 are feasible but not optimal.

Please log in or register to report this question.

3.

The assignment cost of assigning any one operator to any one machine is given in the following table :

MachinesOperators
IIIIIIIV
U1051315
V39183
W10732
X51197

The optimal assignment is :

Exam Year(s)

MH SET - 2019, SET Exam - 2019,

Answer: B

The optimal assignment is U \(\to\) II, V \(\to\) IV, W \(\to\) III, X \(\to\) I, at a total cost of 16.

Hungarian method. Subtract each row minimum (5, 3, 2, 5):

U: 5, 0, 8, 10; V: 0, 6, 15, 0; W: 8, 5, 1, 0; X: 0, 6, 4, 2.

Column minima are 0, 0, 1, 0; subtracting 1 from column III gives U: 5, 0, 7, 10; V: 0, 6, 14, 0; W: 8, 5, 0, 0; X: 0, 6, 3, 2. A full set of independent zeros is U-II, V-IV, W-III, X-I, so this assignment is optimal, with cost \(5 + 3 + 3 + 5 = 16\) (the total reduction \(15 + 1\)).

The other options cost far more: U-II, V-III, W-I, X-IV costs \(5 + 18 + 10 + 7 = 40\); U-III, V-IV, W-II, X-I costs \(13 + 3 + 7 + 5 = 28\); U-IV, V-II, W-III, X-I costs \(15 + 9 + 3 + 5 = 32\).

Please log in or register to report this question.

Answer: C

The Hungarian method rests on the fact that the optimal assignment is not affected by adding or subtracting a constant from any row or column.

Adding or subtracting a constant from every entry of a row (or column) changes the cost of every complete assignment by exactly that constant, because every assignment uses exactly one cell in each row and column. The ranking of assignments, and so the optimum, stays the same. The method uses this to reduce rows and columns until enough zeros appear.

Option A states only the subtraction half of the theorem. Option B is wrong because the objective value does change, by the constant. Option D misdescribes the procedure: entries are reduced row by row and column by column, not one at a time.

Please log in or register to report this question.

5.

Assign the programmers U, V, W to the programmes I, II, III in such way that the total computer time is minimum. The estimated computer time required by the programmers to execute the programmes is given in the table.

Programmes / ProgrammersUVW
I12010080
II8090110
III110140120

The optimal assignment is :

Exam Year(s)

MH SET - 2021, SET Exam - 2021,

Answer: A

The optimal assignment is I → W, II → V, III → U, with total time 280.

With three programmers there are only six assignments, so they can be compared directly:

Assignment (I, II, III)Total
U, V, W120 + 90 + 120 = 330
U, W, V120 + 110 + 140 = 370
V, U, W100 + 80 + 120 = 300
V, W, U100 + 110 + 110 = 320
W, U, V80 + 80 + 140 = 300
W, V, U80 + 90 + 110 = 280

The Hungarian method gives the same result. Option B costs 300 and option C 370, and an optimal assignment always exists for a square cost table, so D is wrong.

Please log in or register to report this question.

Loading…

Other Subjects

Tags: Assignment Problems Questions and Answers || Assignment Problems MCQ Questions and Answers || Assignment Problems GK Questions and Answers || Assignment Problems GK MCQ Questions || Assignment Problems Multiple Choice Questions and Answers || Assignment Problems GK || GK on Assignment Problems || Operations Research Questions and Answers || Operations Research MCQ Questions and Answers || Operations Research GK Questions and Answers || GK on Operations Research