Economic Analysis of Energy Projects Questions and Answers

Answer: A

A board choosing between a lighting change and an insulation scheme needs to know that one runs for five years and the other for twenty-five, which payback conceals. Adding a present value column costs little and changes the ranking.

Please log in or register to report this question.

Answer: B

Correct answer: the capital was rationed and better measures competed for it

A measure inside the hurdle is worth doing in isolation, and it can still be refused if there is not enough capital for everything that qualifies. Under rationing the projects are ranked and the budget is spent from the top, so a perfectly acceptable measure may fall below the line.

Please log in or register to report this question.

Answer: C

Correct answer: both the assertion and the reason are true and the reason explains the assertion

Both are true and the reason gives the mechanism. Payback counts only until the capital is recovered, so it is blind to the project’s remaining life, and it treats a rupee in year three as equal to one today. Those two omissions are exactly why it is used as a screen and backed by a discounted measure before a decision is taken.

Please log in or register to report this question.

Answer: D

In present terms the benefits are indeed the smaller, which is what the negative value states, but the project may still return more than it cost in absolute money. What it fails to do is beat the return the capital could earn elsewhere, which is a different and weaker charge.

Please log in or register to report this question.

Answer: A

Cash flows in today's money must meet a real rate and inflated cash flows a nominal one, and consistently applied either gives the same answer. Mixing them, by discounting today's-money savings at a nominal rate, understates every project.

Please log in or register to report this question.

Answer: B

Maintenance persists for the whole life and may differ between the options, so it belongs alongside capital and energy. The audit fee is a sunk cost, and the other two have nothing to do with the choice between the alternatives.

Please log in or register to report this question.

Loading…
Tags: Economic Analysis of Energy Projects Questions and Answers || Economic Analysis of Energy Projects MCQ Questions and Answers || Economic Analysis of Energy Projects GK Questions and Answers || Economic Analysis of Energy Projects GK MCQ Questions || Economic Analysis of Energy Projects Multiple Choice Questions and Answers || Economic Analysis of Energy Projects GK || GK on Economic Analysis of Energy Projects || Energy Audit Questions and Answers || Energy Audit MCQ Questions and Answers || Energy Audit GK Questions and Answers || GK on Energy Audit