Scheduling and Sequencing Questions and Answers

1.

Parts P1-P7 are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completion time required for carrying out both the operations for all 7 parts is __________ hours.

Part No.Milling (hours)Polishing (hours)
P186
P232
P334
P446
P557
P664
P721

Exam Year(s)

GATE ME - 2022,

Answer: B

The minimum total completion time is 33 hours.

Two machines in a fixed order is the case solved by Johnson's rule: parts whose milling time is less than their polishing time go first, in increasing order of milling time; the rest go last, in decreasing order of polishing time.

  • Milling less than polishing: P3 (3, 4), P4 (4, 6), P5 (5, 7), in that order.
  • The rest, by decreasing polishing time: P1 (6), P6 (4), P2 (2), P7 (1).

Sequence P3, P4, P5, P1, P6, P2, P7. Milling ends at 3, 7, 12, 20, 26, 29, 31 hours. Each polishing job starts at the later of its milling end and the previous polishing end:

PartPolish startPolish end
P337
P4713
P51320
P12026
P62630
P23032
P73233

The last part finishes polishing at 33 hours. 31 is only the total milling time, which ignores the final part's polishing; no sequence can finish in 30 or 32, since Johnson's rule gives the minimum.

Please log in or register to report this question.

2.

Four jobs are on order in a factory. As on day 20 of the production calendar, the corresponding due date and work remaining to complete these jobs (in days) are given in the table below.

JobDue dateWork remaining (in days)
M265
N2410
O2810
P315

Which job(s) has/have critical ratio less than unity?

Exam Year(s)

GATE ME - 2026,

Answer: A

The jobs with critical ratio below one are Job N and Job O.

Critical ratio = (time remaining until due date) / (work remaining). On day 20:

\[ \begin{aligned} M &: (26 - 20)/5 = 1.2 \\ N &: (24 - 20)/10 = 0.4 \\ O &: (28 - 20)/10 = 0.8 \\ P &: (31 - 20)/5 = 2.2 \end{aligned} \]

A ratio below 1 means the job is behind schedule. Only N and O qualify. M and P are ahead of schedule, so the options containing them are wrong.

Please log in or register to report this question.

Loading…
Tags: Scheduling and Sequencing Questions and Answers || Scheduling and Sequencing MCQ Questions and Answers || Scheduling and Sequencing GK Questions and Answers || Scheduling and Sequencing GK MCQ Questions || Scheduling and Sequencing Multiple Choice Questions and Answers || Scheduling and Sequencing GK || GK on Scheduling and Sequencing || Production Planning and Control Questions and Answers || Production Planning and Control MCQ Questions and Answers || Production Planning and Control GK Questions and Answers || GK on Production Planning and Control