Agro Processing Plant Design Questions and Answers

Answer: C

Correct answer: Land, buildings and equipment

Fixed capital is what is spent once to create the plant: land, buildings, equipment, installation, piping, instrumentation and engineering. Raw material, wages and utilities are recurring operating costs, and interest is a financing charge.

Please log in or register to report this question.

Answer: D

Correct answer: Stocks, work in progress and receivables

Working capital is the money tied up in running the plant: raw material stocks, work in progress, finished goods, receivables and cash, less what is owed to suppliers. It is recovered at the end of the project rather than depreciated - and in a seasonal plant it is unusually large, since a year’s raw material may have to be bought in one season.

Please log in or register to report this question.

Answer: A

Correct answer: Total revenue equals total cost

At breakeven the plant makes neither profit nor loss:

\[ Q_{BE} = \frac{\text{Fixed cost}}{\text{Price} - \text{Variable cost per unit}} \]

The denominator is the contribution per tonne - what each tonne contributes towards the fixed costs once its own variable cost has been met.

Please log in or register to report this question.

Answer: B

Correct answer: Time for cumulative inflow to equal the outlay

The payback period is how long the investment takes to return its own cost:

\[ \text{Payback} = \frac{\text{Initial outlay}}{\text{Annual net cash inflow}} \]

It is simple and widely used as a first screen, but it ignores everything after the payback point and takes no account of the time value of money.

Please log in or register to report this question.

15.

Effluent from a fruit and vegetable processing plant is characterised chiefly by

Answer: C

Correct answer: A high biochemical oxygen demand

Fruit and vegetable effluent carries sugars, starches, pulp and washings - all readily biodegradable - so its BOD is high, often several thousand mg/l. That makes biological treatment the natural choice, and it also makes the effluent a candidate for anaerobic digestion, since the organic load is an energy source.

Please log in or register to report this question.

Answer: D

Correct answer: Steam, electricity, water, air, refrigeration

A processing plant needs the whole set: steam for blanching, cooking and sterilising; electricity for drives; water for washing and cooling; compressed air for controls and pneumatics; and refrigeration for chilling and cold storage. Each has to be sized, and each is a running cost.

Please log in or register to report this question.

Answer: A

Correct answer: Consumers do not all peak together

The diversity factor recognises that the sum of individual peak demands overstates the real maximum, because the consumers do not all peak at the same instant. Sizing a boiler or a transformer on the simple sum would mean paying for capacity that is never used at once.

Please log in or register to report this question.

Answer: B

Correct answer: Delivered equipment cost times a factor

The Lang factor method estimates fixed capital as

\[ FCI = f_L \times C_{equipment} \]

with \(f_L\) around 3 for a solids plant, 4 to 5 for a mixed one and above 5 for a fluid processing plant. The factor covers installation, piping, instrumentation, buildings and engineering - everything the equipment alone does not.

Please log in or register to report this question.

Answer: C

Correct answer: Scale a plant cost to another capacity

The six-tenths rule scales cost with capacity:

\[ C_2 = C_1\left(\frac{Q_2}{Q_1}\right)^{0.6} \]

The exponent below one is the economy of scale: a vessel’s cost follows its surface area while its capacity follows its volume, so doubling the throughput costs about 52 per cent more, not 100.

Please log in or register to report this question.

Answer: D

Correct answer: Test the process at intermediate scale

A pilot plant tests at a scale between the laboratory and the works, where the problems of continuous operation, heat transfer, handling and fouling first appear. It is far cheaper to discover them there than in a full-scale plant, and the data it gives is what makes a confident scale-up possible.

Please log in or register to report this question.

Loading…
Tags: Agro Processing Plant Design Questions and Answers || Agro Processing Plant Design MCQ Questions and Answers || Agro Processing Plant Design GK Questions and Answers || Agro Processing Plant Design GK MCQ Questions || Agro Processing Plant Design Multiple Choice Questions and Answers || Agro Processing Plant Design GK || GK on Agro Processing Plant Design || Agricultural Process Engineering Questions and Answers || Agricultural Process Engineering MCQ Questions and Answers || Agricultural Process Engineering GK Questions and Answers || GK on Agricultural Process Engineering