41.

A and B can do a work in 45 and 40 days respectively. They began the work together, but A left after some days and B finished the remaining work in 23 days. After how many days did A leave?

Answer: C

Let the total work be LCM(45,40)=360 units. A's rate=8, B's rate=9 units/day. B worked alone for the last 23 days, so work done by B alone = \(23 \times 9 = 207\) units. Work done by A and B together = \(360 - 207 = 153\) units. Combined rate of A and B = 8+9=17 units/day. Time they worked together = 153/17 = 9 days. So, A left after 9 days.

Please log in or register to report this question.

42.

A man, a woman and a boy can together complete a piece of work in 3 days. If a man alone can do it in 6 days and a boy alone in 18 days, how long will a woman alone take to complete the work?

Answer: A

Combined one day's work = 1/3. Man's one day work = 1/6. Boy's one day work = 1/18. Woman's one day work = \(1/3 - (1/6+1/18) = 1/3 - (3+1)/18 = 1/3 - 4/18 = 1/3 - 2/9 = (3-2)/9 = 1/9\). A woman alone will take 9 days.

Please log in or register to report this question.

43.

X is 50% more efficient than Y. If Y can do a work in 30 days, then in how many days can X and Y together do the work?

Answer: B

50% more efficient means X does the work in \( \tfrac{2}{3} \) of Y's time.

\[ t_{X} = \frac{2}{3} \times 30 = 20 \text{ days} \]

\[ \frac{1}{20} + \frac{1}{30} = \frac{3 + 2}{60} = \frac{1}{12} \]

\[ t = 12 \text{ days} \]

Please log in or register to report this question.

44.

A and B undertake a piece of work for Rs. 1200. A alone can do it in 15 days and B alone in 12 days. With the help of C they finish it in 5 days. What is C’s share of the wage?

Answer: B

Correct answer: Rs. 300

Wages divide in the ratio of work actually done, which for a common period is the ratio of the daily rates.

All three together complete the job in 5 days, so their combined rate is \(\tfrac{1}{5}\). Subtracting A and B gives C’s rate:

\[\frac{1}{5} - \frac{1}{15} - \frac{1}{12} = \frac{12}{60} - \frac{4}{60} - \frac{5}{60} = \frac{3}{60} = \frac{1}{20}\]

So the rates are \(\tfrac{1}{15} : \tfrac{1}{12} : \tfrac{1}{20}\), which on multiplying by 60 becomes \(4 : 5 : 3\).

\[\text{C’s share} = \frac{3}{4+5+3} \times 1200 = \frac{3}{12} \times 1200 = 300\]

Please log in or register to report this question.

45.

A can do a piece of work in 12 days and B in 18 days. Working together, in how many days will they finish it ?

Answer: C

Correct answer: 7.2 days

Add the daily rates rather than the times.

\[\frac{1}{12} + \frac{1}{18} = \frac{3}{36} + \frac{2}{36} = \frac{5}{36}\]

Working at five thirty-sixths of the job per day, they need

\[\frac{36}{5} = 7.2 \text{ days}\]

Please log in or register to report this question.

46.

A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:

Answer: C

Work in rates: someone who finishes a job in \( n \) days does \( \tfrac{1}{n} \) of it a day, and rates add.

\[ \frac{1}{16} + \frac{1}{12} + \frac{1}{C} = \frac{1}{4} \]

\[ \frac{1}{C} = \frac{12}{48} - \frac{3 + 4}{48} = \frac{5}{48} \]

\[ C = \frac{48}{5} = 9\tfrac{3}{5} \text{ days} \]

Please log in or register to report this question.

47.

A, B, and C can do a job in 6, 12 and 15 days respectively. After 1/8 of the work is completed, C leaves the job. Rest of the work is done by A and B together. Time taken to complete the rest of the work is:

Answer: A

Work in rates: someone who finishes a job in \( n \) days does \( \tfrac{1}{n} \) of it a day, and rates add.

Once \( \tfrac{1}{8} \) is done, \( \tfrac{7}{8} \) remains for A and B:

\[ \frac{1}{6} + \frac{1}{12} = \frac{2 + 1}{12} = \frac{1}{4} \]

\[ t = \frac{7}{8} \div \frac{1}{4} = \frac{7}{8} \times 4 = 3.5 = 3\tfrac{1}{2} \text{ days} \]

C's rate never enters the calculation, since C leaves before the stretch being timed.

Please log in or register to report this question.

48.

A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:

Answer: B

Let the original number of workers be x. Using the man-days formula M1*D1 = M2*D2. \(x \times 100 = (x-10) \times 110 \Rightarrow 100x = 110x - 1100 \Rightarrow 10x = 1100 \Rightarrow x = 110\). The original number of workers was 110.

Please log in or register to report this question.

49.

A and B can do a work in 10 days. They start the work together but A leaves after 2 days and B completes the rest of the work in 12 days. In how many days can A do the work alone?

Answer: D

Work done by A and B in 2 days = 2/10 = 1/5. Remaining work = 4/5. B completes 4/5 of the work in 12 days. So B can complete the full work in \(12 \times 5/4 = 15\) days. B's one day work is 1/15. (A+B)'s one day work is 1/10. A's one day work = \(1/10 - 1/15 = (3-2)/30 = 1/30\). A alone takes 30 days.

Please log in or register to report this question.

50.

A can do 1/3 of a work in 5 days and B can do 2/5 of the work in 10 days. In how many days both A and B together can do the work?

Answer: C

A can do the full work in \(5 \times 3 = 15\) days. B can do the full work in \(10 \times 5/2 = 25\) days. A's 1 day work = 1/15. B's 1 day work = 1/25. Together, their 1 day work = \(1/15 + 1/25 = (5+3)/75 = 8/75\). They will take 75/8 = 9 3/8 days.

Please log in or register to report this question.