Agro Processing Plant Design Questions and Answers

51.

Consider the following pairs of estimating method and what it does:

Lang factor - Scales equipment cost to total fixed capital

Six-tenths rule - Scales a plant cost to a different capacity

Breakeven analysis - Finds the output where revenue meets cost

Payback period - Accounts for the time value of money

How many of the pairs given above are correctly matched?

Answer: C

Correct answer: Only three

Three are correctly described. The fourth is not: payback ignores the time value of money entirely - it simply counts undiscounted cash until the outlay is recovered. That, with its blindness to everything after the payback point, is why it is a screening measure rather than a decision rule.

Please log in or register to report this question.

52.

Consider the following pairs of layout requirement and its purpose:

Unidirectional flow - Preventing cross-contamination

Drainable, crevice-free equipment - Reliable cleaning

Short material paths - Lower handling cost and damage

Symmetrical equipment placement - Preventing cross-contamination

How many of the pairs given above are correctly matched?

Answer: D

Correct answer: Only three

Unidirectional flow, drainable equipment and short paths are all correctly matched to their purposes. Symmetrical placement is not a hygiene measure at all - it is an aesthetic or structural convenience, and symmetry does nothing to keep raw and finished product apart.

Please log in or register to report this question.

53.

Three of the following are fixed capital items. Which is working capital?

Raw material stocks

Process equipment

Buildings

Equipment installation

Answer: A

Correct answer: Raw material stocks

Raw material stocks are working capital: money tied up in the goods themselves, recovered when the product is sold. Equipment, buildings and installation are all one-off fixed capital, written down over the plant’s life.

Please log in or register to report this question.

54.

Three of the following are governed by the layout. Which is not?

The plant's rated throughput

Material travel distance

Cross-contamination risk

Handling cost per tonne

Answer: B

Correct answer: The plant's rated throughput

Throughput is set by the capacities of the machines - specifically by the slowest of them - not by where they stand. Layout governs travel distance, handling cost and contamination risk; it can waste a plant’s capacity but cannot create any.

Please log in or register to report this question.

55.

Three of the following raise a plant's breakeven output. Which lowers it?

A higher selling price per tonne

Higher fixed costs

A higher variable cost per tonne

A larger depreciation charge

Answer: C

Correct answer: A higher selling price per tonne

Breakeven is fixed cost divided by contribution, and a higher price raises the contribution, so the breakeven output falls. Higher fixed costs raise the numerator; a higher variable cost cuts the contribution; and depreciation is itself a fixed cost. All three of those push breakeven up.

Please log in or register to report this question.

56.

Three of the following are utilities. Which is a process operation?

Pasteurisation

Steam

Compressed air

Refrigeration

Answer: D

Correct answer: Pasteurisation

Pasteurisation is a process operation - something done to the product. Steam, compressed air and refrigeration are utilities: services generated centrally and distributed to whichever operation needs them. Pasteurisation is in fact a consumer of the steam.

Please log in or register to report this question.

57.

Three of the following reduce technical risk in a new plant. Which increases it?

Scaling directly from laboratory to full size

Building a pilot plant first

Using established equipment types

Testing the process on the actual raw material

Answer: A

Correct answer: Scaling directly from laboratory to full size

Going straight from bench to full scale is the classic way to be surprised: heat transfer, mixing, handling and fouling all behave differently at size, and the raw material in the field is never as uniform as the sample in the laboratory. A pilot plant, established equipment and trials on the actual crop all reduce that risk; skipping the intermediate step increases it.

Please log in or register to report this question.

58.

A mango pulping plant is being sited. The fruit is bulky and perishable and the pulp is shelf-stable in aseptic packs.

Where should the plant be built?

Answer: B

Correct answer: Near the orchards, the fruit being perishable

The raw material is bulky and perishable and the product is stable and compact, so the transport problem lies on the inbound side. Siting near the orchards gets the fruit into process while it is fresh and avoids hauling water and skin that will be discarded anyway. The aseptic pulp can then travel any distance.

Please log in or register to report this question.

59.

A line rated at 6 t/h is found to deliver only 4.5 t/h, and material accumulates ahead of one machine.

What should be done first?

Answer: C

Correct answer: Uprate the limiting stage, then the next

The line is delivering the capacity of its slowest stage, and material accumulating in front of one machine identifies it. Uprate that one, then look again - the next slowest becomes the constraint, and debottlenecking proceeds one stage at a time. Uprating everything equally would spend far more for the same result.

Please log in or register to report this question.

60.

A food plant's layout brings the finished product despatch bay past the raw material reception area.

What is the principal objection?

Answer: D

Layout is a preventive control, and a plan that brings raw and finished material together will eventually transfer contamination whatever the cleaning regime. Unidirectional flow from dirty to clean is the governing principle.

Please log in or register to report this question.

Loading…
Tags: Agro Processing Plant Design Questions and Answers || Agro Processing Plant Design MCQ Questions and Answers || Agro Processing Plant Design GK Questions and Answers || Agro Processing Plant Design GK MCQ Questions || Agro Processing Plant Design Multiple Choice Questions and Answers || Agro Processing Plant Design GK || GK on Agro Processing Plant Design || Agricultural Process Engineering Questions and Answers || Agricultural Process Engineering MCQ Questions and Answers || Agricultural Process Engineering GK Questions and Answers || GK on Agricultural Process Engineering